CELGAS - Conventional and e-Learning Gas Engineering Centre


WP3: Creation of learning material & test course development

Each module presented in fig.1 work plan for test courses (preparation of material: WP3.1-WP3.5) have similar construction. Each structural work plan is based on sub-tasks:

  1. Detailed task and products definition
  2. PM pre writing course meeting
  3. Detailed definition task and products
  4. Creation of learning material
  5. Course production
  6. PM internal quality evaluation
  7. Enrolment and course dissemination
  8. Iteration of quality
  9. Outside experts evaluation
  10. PM improvement of course
  11. Start of testing course and continuing course
  12. Mid Course Meeting
  13. Exams
  14. PM quality sum and correction
Fig. 3. The mind map of total training preparation and implementation process

In the preparation of learning material in the ICT format all Partners will assume help of subcontractors - quality e-learning companies, which will produce high quality multimedia sources (slides, graphics, presentations, films, virtual labs etc). The primary role of subcontractors is add quality support to the content of e-learning experimental courses (WP3). This allows concentrating of main partners on the engineering and educational input of course instead realizes total courses production.

Below are presented details of each work packages WP3.1-WP3.5.

Start and Finish date and overall duration of whole WP3

Start after WP2 to end of task - total duration 291 days.

Total number of staff days
WP3
Managers (ISCO 1) 129.4
Researchers (ISCO 210, 220, 240) 192.1
Teachers/trainers (ISCO 230) 113.1
Technical (ISCO 3) 114.0
Administrative (ISCO 4) 70.6

Role and task of partners

Responsible for whole WP3 work package is P7. Details are presented in description of WP.3.1-3.5.


Working methods and techniques

See details in WP3.1-3.5

WP3.1: Developments in Production of Gas: course of integrated management of reservoir

WP3.2: Underground Gas Storages: course for integrated management of Underground Gas Storage

WP3.3: Gas Distribution - The "GIS" Technique in the GAS DISTRIBUTION MANAGEMENT

WP3.4: Gas Usage, End User Safety and Environmental Protection

WP3.5: Quality Management and Human Resources Management in Gas Engineering - PERSON QUALITY

created by: ziz.pl